North East Middle/High School Construction Project
Community Update Meeting: Project Progress
Wednesday, May 24, 2023 at 4:00PM
Carver Center (201 Booth Street, Elkton) With Virtual Livestream
Design: May 2022 - August 2023
Phase 1 - Middle School
Construction: June 2023 - June 2026
Move In: June - August 2026
Start School: August 2026
Phase 2 - High School
Construction: August 2026 - June 2029
Move In: June - August 2029
Start School: August 2029
Phase 3 - Demolition and site completion
August 2029 - May 2030